Expansion of the South Bay International Wastewater Treatment Plant is underway. Staff photo by Madeline Yang.

As the U.S. and Mexico work on multiple projects to address the Tijuana sewage crisis, elected officials are saying millions in funding is lacking.

Mexico’s untreated wastewater has for years polluted the coastline of south San Diego County, resulting in health hazards, beach closures and economic damage to Imperial Beach and Coronado.

According to the U.S. Environmental Protection Agency (EPA), the first major construction contract for expansion of the South Bay International Wastewater Treatment Plant was awarded in September 2026 with construction beginning soon after. That project will expand treatment capacity to 50 million gallons per day (MGD).

Full design of the expansion and approval was slated for October 2026, according to the EPA and International Boundary and Wastewater Commission (IBWC).

On Nov. 13, Frank Fisher, spokesman for the IBWC, told The Coronado News design for 50 MGD is completed.

In June, the EPA announced full expansion was advancing on schedule.

A Memorandum of Understanding between the United States and Mexico, signed in July 2025, identifies December 2027 as the deadline for this project.

But federal funding beyond the $650 million secured to rehabilitate and expand the plant, currently treating up to 35 million gallons per day, is still needed, according to an Oct. 23 San Diego Association of Governments’ (SANDAG) staff presentation. 

Ryan Williams, manager of government affairs at SANDAG, said bringing the plant to the full 50 million gallons per day of secondary treatment, which is the biological stage needed to meet U.S. standards, is expected to cost about $270 million more. This funding has not yet been secured, he said.

Earlier this year the IBWC told the San Diego Water Board the expansion of secondary treatment is targeted for 2030. 

Engineering News-Record reports a revised contract, of $552 million, the IBWC awarded PCL Construction on Oct. 13 is for expansion of the plant’s primary treatment facilities with substantial completion scheduled for 2031.

That amount does not include expansion of the plant’s secondary treatment facilities with Fisher confirming additional funding will be required, according to Engineering News-Record in October.

That month IBWC told The Coronado News it had no comment about when it anticipates funding for secondary treatment of the plant’s expansion to 50 MGD, nor the impact to the project’s timeline.

“We learned that IBWC is saying that they’re already short $200 million to fix the plant, that was news to many of the congressional members,” said County Supervisor Paloma Aguirre, after SANDAG’s presentation. 

In September, the Board of Supervisors approved the Tijuana River Capture and Cleanup Initiative and is currently evaluating the first phase of a project to build a new treatment plant, separate from the existing South Bay facility, to capture and treat Tijuana River sewage flows.

Aguirre has proposed to use funding from Measure B, a Nov. 3 ballot measure that appears to have passed and will raise the sales tax by a half-cent, from 7.75% to 8.25% in Coronado.

The ballot measure would raise up to $450 million annually for health and safety services in San Diego County, including the sewage pollution in Tijuana River Valley. Unofficial election results, as of Nov. 12, show a majority of voters support the measure with 53.2% voting yes.

During the SANDAG meeting, Coronado Mayor John Duncan expressed concerns about additional sewage resulting from a new desalination plant and Tijuana’s population growth. 

Duncan supports an enforcement mechanism through the United States–Mexico–Canada Agreement. He noted Imperial Beach and Coronado passed resolutions asking the federal government to enforce penalties and consequences for Mexico to address beach closures.

“I am frustrated because the Trump administration and the EPA administrator came to Coronado, stood with us and said, ‘We’re going to do 100% solution,’” said Duncan. “…There is no 100% solution proposed.”

San Diego Water Board Executive Officer David Gibson also addressed funding shortages for the international plant expansion during a report in November.

“They are still currently reporting to us, IBWC, that they’re $275 million short of the full design construction cost as projected today… for the secondary treatment system,” said Gibson on Nov. 10.

Gibson said he has emphasized the board’s expectations to the IBWC multiple times.

“The board’s expectation is that the plant will be expanded by 2030 and at full secondary for …whatever they ultimately design,” said Gibson.

More News

Julieta is a reporter for The Coronado News, covering education, small business and investigating the Tijuana/Coronado sewage issue. She graduated from UC Berkeley where she studied English, Spanish, and Journalism. Apart from reporting, Julieta enjoys reading, traveling, and spending quality time with family and friends.